25.1. For the purposes of this Subdivision, acceptance is deemed to have taken place not later than 6 months after receipt of the notice of the end of work if the following conditions are met:
(1)  the work is completed;
(2)  the syndicate is formed and is no longer under the control of the contractor;
(3)  the notice of the end of work sent to the syndicate by the contractor, at the time the syndicate was no longer controlled by the contractor, informed the syndicate of the end of the work and obligations with respect to acceptance;
(4)  six months have elapsed since the receipt of the notice by the syndicate and the latter, without reason, did not accept the common portions.
O.C. 39-2006, s. 10; O.C. 156-2014, s. 14.
25.1. For the purposes of this Subdivision, acceptance is deemed to have taken place not later than 6 months after receipt of the notice of the end of work if the following conditions are met:
(1)  the work is completed;
(2)  the syndicate is formed and is no longer under the control of the contractor;
(3)  the notice of the end of work sent to the syndicate by the contractor informed the syndicate of the end of the work and obligations with respect to acceptance; and
(4)  six months have elapsed since the receipt of the notice by the syndicate and the latter, without reason, did not accept the common portions.
O.C. 39-2006, s. 10.